28 Oct 5 – Marching Orders
The dumpster was delivered and ready to go.
Our prescribed order of operations for getting the shell of the room back together are as follows:
- Demo the ceiling and remove it from the rafter ties.
- Remove every other rafter tie and double up the existing ones.
- Rough in the new electrics in the ceiling and walls.
- Fill in the spaces between the roof rafters with insulation.
- Cover the roof rafters with a layer of 1/2” OSB (Oriented Strand Board)
- Add a layer of 5/8” drywall over the OSB
- Paint, paint, paint, paint, and paint (since we’re removing the carpet it’ll be the perfect drop cloth)
- Pull up the carpet
- On top of the homasote subfloor put down a specific floor pad
- On top of the floor pad float an engineered hardwood floor
That’s our Phase 1. Should be quick to do right?